Homeowner
Communication - July 6, 2010
Dear Homeowner:
I hope you and your family had a wonderful
Fourth of July holiday. It is truly a special
time for our country.
Since our last update, we have been working
closely with the Rivermist HOA to advance
final approvals for the retaining wall plans.
Additionally, our team continues to make
progress on the site preparation work as
we ready the area for the upcoming retaining
wall construction. The purpose of this letter
is to update you on our progress in both
of these important areas.
Plan Review Process
We are pleased to report that the team of
third-party engineering experts has completed
its comprehensive analysis of the retaining
wall plans, allowing us to submit these
plans to the Rivermist HOA and the City
of San Antonio last week. Once the plans
are approved by the HOA and permitted by
the City of San Antonio, we can immediately
begin construction of the new pier-panel
retaining wall. An animation of the wall
can be found at rivermistinfo.com.
Storm
Drain Repaired
As you know, during the January slope failure,
the storm drain for Treewell Glen and surrounding
streets was damaged. While the drain has
been undergoing repairs, we have pumped
excess rainwater into temporary drainage
swales within the area. We can report that
the drain has been repaired and that pumping
is no longer necessary. All excess water
will now drain through the rebuilt underground
infrastructure.
Continued Site Preparatory Work
With the drain repaired, we can finish construction
of the “bench” that will support
the drilling equipment required for installation
of the wall piers in the slope. We have
constructed approximately 50 percent of
the bench and should complete the project
within the next two weeks. Once the site
preparation work is complete and the approvals/permits
received, we can move immediately to begin
construction of the new retaining wall.
Again, thank you for your continued patience
and support. As always, feel free to contact
me with any questions or concerns at rivermist@centex.com.
Sincerely,
Laurin Darnell
Homeowner Communication
- June 18, 2010
Dear Homeowner:
You have probably noticed that Centex has begun preparing the site for construction of the new retaining wall. You may also know from recent news reports that we continue collecting and analyzing data regarding the wall design in response to requests for additional information from the Rivermist Homeowners Association (HOA) engineers. The purpose of this letter is to provide you with a status report on these concurrent efforts.
Site preparation
Centex received approval June 7 from the City of San Antonio and the Rivermist HOA to immediately begin the preparatory work that will ready the area for the new multi-million dollar pier panel wall system. The site work is anticipated to take approximately four weeks, barring any additional weather delays. We are currently working approximately ten hours per day, five days per week. We appreciate your patience and apologize for any inconvenience the work may cause you. The site preparation allows our team to get a head start on constructing the new wall while engineers from Centex, the City and the HOA continue to review the wall design plans.
Plan review process
At a May 21 meeting between Centex, the City and the HOA, Centex was asked to provide more data regarding the engineering design of the proposed wall (an animation of which may be viewed at rivermistinfo.com). Centex continues to collect and supply this additional information and has enlisted the help of an additional third-party expert, Garry Gregory, P.E., Ph.D., of Oklahoma State University. Dr. Gregory is the author of modeling software widely used to measure slope stability. This additional data analysis, which follows the peer reviews by experts from the University of Texas at Austin, University of Illinois at Champagne-Urbana, Terracon Consultants, Inc. and the HOA’s engineering consultants, is expected to take an additional four weeks. If all goes according to plan, Dr. Gregory’s review will be completed at approximately the same time the site work is finished, allowing Centex to submit a final design plan to the City and HOA for approval.
Realtor outreach
As I mentioned in our May 27 letter, we continue to welcome new neighbors to the community. Since the January 24 slope failure, Centex has sold 15 new homes between the three Rivermist communities, all at prices consistent with sales before the slope failure. We’ve also begun an effort to educate realtors on our plans to rebuild the wall. After several meetings with large brokerages that specialize in this area, we’ve gotten positive feedback that the Rivermist communities remain highly desirable and marketable.
Again, thank you for your continued patience and support. As always, feel free to contact me with any questions or concerns at rivermist@centex.com.
Sincerely,
Laurin Darnell
Homeowner
Communication - May 1, 2010
Dear Homeowner,
I am pleased to report that the slope stabilization
is officially complete. More than 130 stabilization
piers were inserted into the slope over
the last few months. The 30 foot-deep piers
were installed vertically in a grid pattern
across the slope to increase resistance
to slope movement. Although the slope was
temporarily stabilized following the January
24 failure, third-party engineers advised
Centex to install the stabilization piers
as an added measure to reinforce the failed
slope area. The image below is of the final
pier being installed.

Additionally, I wanted to let you know
we have completed the engineering plans
for the new retaining wall system in the
Hills of Rivermist community.
Our design plans were completed earlier
this week, and while we’ve been targeting
an April 30th submission date, we are allowing
a few additional days to ensure a thorough
peer review process by nationally recognized
third-party experts. Taking the time necessary
to conduct this rigorous review process
will provide the best permanent solution
for the community - a solution in which
you, the homeowner, can have the highest
degree of confidence.
The design was produced by Craig Olden,
Inc., a Texas-based industry leader with
35 years experience in the design and construction
of retention systems.
The plans are now undergoing a rigorous
peer review by multiple third-party experts,
including:
- Terracon Consultants, Inc., a geotechnical
engineering firm retained by Centex after
the Jan. 24 slope failure
- Reed Engineering Group, a geotechnical
engineering firm based in Dallas
- Stephen G. Wright, Ph.D, an expert in
geotechnical engineering, soil mechanics
and slope stability at The University
of Texas at Austin’s Cockrell School
of Engineering
- Timothy D. Stark, Ph.D, an expert in
soil mechanics, foundation engineering
and the stability of natural and manmade
slopes at the University of Illinois at
Urbana-Champaign
Upon completion of the peer-review, the
plans will be submitted to the City of San
Antonio as part of Centex’s permit
application. The plans will also be provided
to the Rivermist Homeowners Association,
which has retained attorneys and consultants
to review the plans on homeowners’
behalf.
We propose building a multi-million dollar
pier-panel wall system, including concrete
piers drilled deep into the ground and steel-reinforced
concrete panels spanning the piers above
ground. A video animation of the wall may
be viewed at rivermistinfo.com.
Pending the issuance of a permit by the
City of San Antonio, we expect to begin
construction within two to three weeks.
The wall will take an estimated six months
to complete.
As always, please feel free to contact me
with questions or concerns at rivermist@centex.com.
Sincerely,
Laurin Darnell
Homeowner Communication
- April 19, 2010
Dear Rivermist Homeowner:
I am pleased to report that despite the
heavy rain this past week, the slope held
up well, indicating that the stabilization
is working as intended. We are nearly finished
installing 120 steel and concrete piers
in the ground throughout the area where
the slope failed. The 30 foot-deep piers
are installed vertically in a grid pattern
across the slope to increase resistance
to slope movement. We’ll gather new
data this week to verify our observations.
Some of you have voiced concern about the
water that accumulated on Treewell Glen
during the storms. The storm drain pipe
that conveys captured water runoff from
Treewell Glen and delivers it to a nearby
creek was damaged during the slope failure
and rendered inoperable. To temporarily
accommodate runoff until the pipe is fixed,
the water is being pumped into a temporary
channel that connects to existing, undamaged
drainage infrastructure.
During the heaviest parts of the rain event,
runoff accumulated on Treewell Glen until
the pumps could catch up. No damage occurred,
and Treewell Glen was passable at all times.
Contract crews were on site Saturday and
Sunday, and additional pumps were brought
in specifically to manage the heavy runoff.
These pumps will be left on site for the
next few weeks. Once the design for the
new wall is approved by the City of San
Antonio, we will move forward with a permanent
drainage improvement. Thank you for your
patience and understanding.
As always, if you have questions and comments,
please e-mail me at rivermist@centex.com.
Sincerely,
Laurin Darnell
Centex Homes
Homeowner Communication
- April 6, 2010
|
| Initial section of the
wall to be removed on April 7 |
|
Dear Homeowner,
There’s been a lot going on this
past week as Centex continues to make progress
toward implementing the solution for the
Rivermist communities.
To date, approximately 50 of the 120 stabilizing
piers have been installed below the surface
level and across the slope failure area.
At this pace, we expect to be completed
by our original target date of 30 days (April
16th). As we previously stated, these piers
stabilize the area so that soil and damaged
portions of the wall can be removed; and
we can begin the process of building the
new wall.
Starting tomorrow morning, we will begin
work on removing large portions of the failed
wall. Removal will coincide with the pier
placement as we move from a north to south
direction. During this time, Centex will
also repair damage on the sewer line. As
you may or may not recall, the sewer is
currently pumped out of a manhole on Treewell
Glen. This will now eliminate the need for
a SAWS vacuum truck to visit Treewell Glen
multiple times a day.
Additionally, Centex is working with the
City regarding the removal of the live oak
trees in the affected area. We will obtain
the necessary approvals and permits. These
trees will be mitigated with new plantings
within the community.
Lastly, Centex continues to make progress
to complete design and engineering plans
for a pier-panel wall system by April 30.
If City approval is received on April 30th,
construction of the new retaining wall could
start in early May and will last approximately
4-6 months from construction start. Click
here to view initial design concepts.
As always, if you have questions and comments,
please e-mail me at Rivermist@centex.com.
Sincerely,
Laurin Darnell
Homeowner
Communication - March 18, 2010
Dear Homeowner:
Today, Centex met with City officials today
to review the independent engineer’s
design concepts to repair the slope and
retaining wall at Rivermist.
As you know, Centex announced last week
that a new retaining wall will be built
across the entire length of the slope below
the street of Treewell Glen.
Presented today were preliminary design
plans for a pier paneled wall system which
consists of reinforced concrete piers driven
to a depth ranging from 10 to 30 feet below
the ground surface and reinforced concrete
panels between the piers. The piers will
be placed approximately 8 to 12 feet apart
along the length of the wall and there are
measures taken into consideration to collect
water and drain it away from behind the
wall.
The City’s initial feedback indicates
the pier panel wall system seems to be the
appropriate design for long-term slope stabilization.
With this preliminary feedback, we intend
to work toward final design and engineering
of the new wall. We expect to finalize that
approval process by April 30. If approvals
are obtained by then, construction of the
new wall system could begin as early as
mid-May.
As always, we will keep you updated via
www.rivermistinfo.com as the work progresses.
Sincerely,
Laurin Darnell
Centex Homes |